MONITORING AND PREDICTING THE PROJECT PROGRESS USING EARNED VALUE ANALYSIS: A CASE STUDY IN MANGALURU

AKSHAYA KRISHNA N, PUSHPARAJ NAIK.

Abstract
Considering the various challenges existing in construction activities, the earned value tool has a
lot of theoretical and practical significance. The entrepreneurs, project managers and experts can apply this
technique to minimize the problems arising in the construction field. This paper focuses on monitoring and
predicting the project progress using earned value technique. In order to prepare schedule and estimation easily,
Primavera P6 software is used.

Key words: Earned value, Scheduling, Primavera, Planned cost, Tracking, Actual cost


 
ARTICLE TOOLS
Abstract
PDF Fulltext
How to cite this articleHow to cite this article
Citation Tools
Related Records
 Articles by AKSHAYA KRISHNA N
Articles by PUSHPARAJ NAIK
on Google
on Google Scholar


How to Cite this Article
Pubmed Style

AKSHAYA KRISHNA N, PUSHPARAJ NAIK. MONITORING AND PREDICTING THE PROJECT PROGRESS USING EARNED VALUE ANALYSIS: A CASE STUDY IN MANGALURU. JCR. 2020; 7(9): 2889-2897. doi:10.31838/jcr.07.09.451


Web Style

AKSHAYA KRISHNA N, PUSHPARAJ NAIK. MONITORING AND PREDICTING THE PROJECT PROGRESS USING EARNED VALUE ANALYSIS: A CASE STUDY IN MANGALURU. http://www.jcreview.com/?mno=130047 [Access: April 14, 2021]. doi:10.31838/jcr.07.09.451


AMA (American Medical Association) Style

AKSHAYA KRISHNA N, PUSHPARAJ NAIK. MONITORING AND PREDICTING THE PROJECT PROGRESS USING EARNED VALUE ANALYSIS: A CASE STUDY IN MANGALURU. JCR. 2020; 7(9): 2889-2897. doi:10.31838/jcr.07.09.451



Vancouver/ICMJE Style

AKSHAYA KRISHNA N, PUSHPARAJ NAIK. MONITORING AND PREDICTING THE PROJECT PROGRESS USING EARNED VALUE ANALYSIS: A CASE STUDY IN MANGALURU. JCR. (2020), [cited April 14, 2021]; 7(9): 2889-2897. doi:10.31838/jcr.07.09.451



Harvard Style

AKSHAYA KRISHNA N, PUSHPARAJ NAIK (2020) MONITORING AND PREDICTING THE PROJECT PROGRESS USING EARNED VALUE ANALYSIS: A CASE STUDY IN MANGALURU. JCR, 7 (9), 2889-2897. doi:10.31838/jcr.07.09.451



Turabian Style

AKSHAYA KRISHNA N, PUSHPARAJ NAIK. 2020. MONITORING AND PREDICTING THE PROJECT PROGRESS USING EARNED VALUE ANALYSIS: A CASE STUDY IN MANGALURU. Journal of Critical Reviews, 7 (9), 2889-2897. doi:10.31838/jcr.07.09.451



Chicago Style

AKSHAYA KRISHNA N, PUSHPARAJ NAIK. "MONITORING AND PREDICTING THE PROJECT PROGRESS USING EARNED VALUE ANALYSIS: A CASE STUDY IN MANGALURU." Journal of Critical Reviews 7 (2020), 2889-2897. doi:10.31838/jcr.07.09.451



MLA (The Modern Language Association) Style

AKSHAYA KRISHNA N, PUSHPARAJ NAIK. "MONITORING AND PREDICTING THE PROJECT PROGRESS USING EARNED VALUE ANALYSIS: A CASE STUDY IN MANGALURU." Journal of Critical Reviews 7.9 (2020), 2889-2897. Print. doi:10.31838/jcr.07.09.451



APA (American Psychological Association) Style

AKSHAYA KRISHNA N, PUSHPARAJ NAIK (2020) MONITORING AND PREDICTING THE PROJECT PROGRESS USING EARNED VALUE ANALYSIS: A CASE STUDY IN MANGALURU. Journal of Critical Reviews, 7 (9), 2889-2897. doi:10.31838/jcr.07.09.451